Articles on: Projects & orders
This article is also available in:

The financial overview of a project

You can call up a financial overview from the project overview: choose the Financial view at the top right. At the top you filter on a period with from and Up to and including: the costs, the invoiced amount and the forecast changes then only count within that period, and projects without activity in that period disappear from the list. With the Excel button you download the overview.


In the financial overview, the columns let you determine which statistics you want to see here.
You choose the columns that are visible in the financial overview yourself in Settings > Projects > Overview > Financial overview.


Columns

Explanation

Estimated costs

The total cost price of quotations + change orders that are active on the project

Estimated yield

The total selling price of quotations + change orders that are active on the project

Effective costs

The total cost price of work orders + incoming invoices + internal supply orders linked to the project

Invoices

The total selling price of all invoices linked to the project

Budgeted margin

(Estimated yield - estimated costs) / estimated yield

Realized margin

Invoices - effective costs - indirect costs realised

Realized margin %

(Invoices - effective costs - indirect costs realised) / invoices

Remaining costs

Forecast - effective costs

Percentage of completion

If the forecast equals 0, you get 0%. Otherwise: (effective costs / forecast) * 100, with a maximum of 100%

Under(-)/over(+) invoiced

Invoices - (estimated yield * percentage of completion)

Forecast

Estimated costs + forecast Δ

Forecast margin

(Estimated yield - forecast) / estimated yield

Forecast Δ

Sum of all forecast changes on the project

Forecast result

Estimated yield - forecast

Indirect costs budgeted

The indirect costs taken from the indirect cost margin on the quotation

Indirect costs realised

(Effective costs + Time & Materials) * the indirect cost margin of the project, per cost type

Indirect costs forecast

The forecast changes * the indirect cost margin of the project, per cost type


How to set the indirect cost margin of a project is explained in How do indirect costs work on a project?


The 'Realized margin %' column follows 3 colours:


  • Green: the realized margin is equal to or higher than the budgeted margin
  • Orange: the realized margin lies between 0 and the budgeted margin
  • Red: the realized margin is lower than 0, or there are already costs but nothing has been invoiced yet

Updated on: 18/11/2026