How do indirect costs work on a project?

With indirect costs you pass on the overhead costs of your company, such as your office, your vehicles and your administration, to your projects. Robaws calculates them with a percentage per cost type: the Indirect cost margin.


Where do you set the indirect cost margin?


  • On the quotation: in the Margins calculation tab, with the Indirect cost margin. That is where the Indirect costs budgeted of the project come from. Read Adding direct and indirect costs to your quotation.
  • On the project: in the Overview tab, Financial block, click the pencil and fill in the Indirect cost margin: Margin item, Margin work, Margin material, Margin OA and Margin other, each in %. That is where the Indirect costs realised and the Indirect costs forecast come from.


A new project starts with an indirect cost margin of 0%. The margins of the quotation are not copied to the project, but those of a project template are. Are your Indirect costs realised at 0? Then fill in the margin on the project, or set it in your project template.


How does Robaws calculate the indirect costs?



Calculation

Indirect costs budgeted

From the indirect cost margin of the active quotations and change orders

Indirect costs realised

(Effective costs + Time & Materials) × the indirect cost margin of the project, per cost type

Indirect costs forecast

The forecast changes × the indirect cost margin of the project, per cost type


The realised indirect costs are deducted from the Realized margin in the financial overview.