How do I have a supply order delivered in parts with call-off orders?
Do you agree a large quantity with your supplier that they deliver in parts, for example all the concrete for a site? Then you place one supply order for the full quantity. Every time you need a part, you create a call-off order: it has part of that supply order delivered. That way you always see how much has already been called off and how much is still outstanding.
Creating a call-off order
You always create a call-off from a supply order of the Supply order type. You can do this in three ways:
- On the supply order, click the plus sign next to 'Call-off orders' in the Overview block.
- On a previous call-off, click the plus sign next to 'Call-off orders' in the Overview block. The new call-off starts from that previous call-off.
- In the overview of your supply orders, click Add (+), choose Call-off and then the supply order.
What is on a call-off?
- The number of the supply order, followed by -1, -2, ... A call-off does not have its own numbering.
- In the Supply order field, the supply order on which the call-off is based.
- The supplier, the status, the extra fields and Consider completed of the supply order.
On the lines you see per item:
Column | Explanation |
|---|---|
Predicted | The quantity on the supply order. |
Previous | What you already called off on previous call-offs. |
Quantity | What you are calling off now. You fill this in yourself. |
Fill in Deliver before and, if applicable, the Delivery address. You type the delivery address yourself, or you click the button next to it and choose a fixed address, the site address of a project or the address of an order that is on the lines. You create fixed addresses in the settings.
Then send the call-off to your supplier with the E-mail action button.
Receiving and invoicing
A call-off does not have its own Received and Invoiced columns. Everything ends up on the supply order:
- If you create a stock change from a call-off, Robaws takes over the lines of the call-off, but adds the received quantity to the supply order.
- If you create an incoming invoice from a call-off, it is linked to the supply order.
In the recalculation of your project only the supply order counts, not the call-offs.